储罐防腐施工方案

目 录
一、工程概况..........................................................2
二、编制依据..........................................................4
三、施工部署..........................................................4
四、施工准............................................................4
五、施工技术方案......................................................5
5.1作业流程图....................................................5
5.2脚手架搭设方案................................................6
5.3表面处理......................................................7
5.4油罐防腐涂漆施工.............................................10
5.5补漆施工.....................................................11
5.6质量检验.....................................................11
六、质量保证措施.....................................................12
七、施工HSE管理措施.................................................12
八、文明施工措施.....................................................14
九、事故应急预案.....................................................14
某输油管线首站罐区配套工程(新建部分) 储罐防腐施工方案
一、工程概况
1、某输油管线首站罐区配套工程防腐工程的施工地点位于浙江省XX市XX镇。此地东临上海,南临杭州湾,而且紧靠东海海边。该地方空气潮湿,对油罐的腐蚀性比较强。
本工程的工程量包括30000 m3内浮顶油罐2座:15000 m3拱顶油罐1座,原有30000 m3油罐底板更换2座。
2、设计参数3万立方罐(单罐)

二、编制依据
某输油管线首站罐区配套工程(A00)《防腐涂漆和表面色规定》
《涂装前钢材表面锈蚀等级和除锈等级》(GB/T8923-88)
《涂膜颜色标准》(GB/T3181-95)
《石油化工设备和管道涂料防腐蚀技术规范》(SH3022-99)
《石油化工设备管道钢结构表面色和标志规定》(SH3043-2003)
《某输油管线首站罐区配套工程—成品油罐组一储罐防腐规格书》
三、施工部署
3.1建立完善的施工管理体系,抽调施工经验丰富的员工组成一线作业层,设
立脚手架搭设、喷砂除锈、涂漆3个班组,科学管理,精心组织,确保优质高效完成该项目施工任务。
施工队长
3.2施工进度计算安排
本防腐工程计划在2007年10月5日开工,2008年1月20日完工。
(具体安排根据现场交付情况进行适当调整)
四、施工准备
1、施工准备
质检员
安全员
技术员
综合班
防腐二班
起重班
喷沙三班
喷沙二班

①技术准备
熟悉施工图纸和设计文件,结合工程具体情况提出技术交底和施工方案等资料,准备齐全与本工程有关的施工标准验收规范及各种记录表格,对工程重要部位、重点环节制定针对性措施,组织编制各分项的具体施工工艺,设置工艺管理卡。
②原材料准备
用于本工程的原材料必须保证出厂合格证、性能检测报告齐全,外包装检查合格,产品在在有效使用期内。
③施工人员准备
所有施工人员施工前必须接受安全培训、技术交底,架子工持证上岗。